Managing the Risks of Bringing Power for the Future on Underground Transmission Line
MORNING SESSION: Simpson Gumpertz & Heger 135 South LaSalle Street, Suite 3800 / EVENING SESSION: The Conference Center at One North Wacker 1 N. Upper Wacker Drive, 2nd Floor
Belmont Light needed to upgrade its aging substation and power transmission and distribution systems to improve reliability and prepare for growing demands. The project involved constructing a new substation in Belmont, Massachusetts, and two 0.8 mile, 115kV buried transmission lines along an existing commuter rail right-of-way connecting area suburbs to Boston. This alignment, while the least disruptive to the community, posed significant technical challenges and at one point was considered practically unbuildable. In this presentation, we will explore this case study and highlight how the project team worked together to manage risks arising from several key challenges, including avoiding various environmental resource areas, excavating alongside an active commuter railway, and dealing with highly varying soil conditions.
After attending this seminar, participants will be able to:
- Discuss design and construction challenges that arose on this project and how they were managed and resolved by the project team.
- Illustrate how the appropriate technology can help overcome challenging site conditions.
- Demonstrate how a proactive approach to involving all stakeholders, including utility owner agencies, during design development can minimize conflicts during construction.
- Discuss the importance of a multidisciplinary approach to meet demanding client needs.
Attendance is free and open to all; please invite colleagues. We will serve refreshments.
SPEAKER: Giuliana A. Zelada, PE, Senior Project Manager. Giuliana Zelada specializes in geotechnical engineering and underground construction. She provides planning, design, risk assessment, and construction support services in the areas of shallow and deep foundation systems, earth retention systems, deep excavations, retaining walls, construction dewatering, and groundwater monitoring for residential, commercial, and industrial buildings, as well as power stations and substations. Giuliana has also participated in several investigations into causes of building and structure settlement and heave, retaining wall failures, and slope failures, and has provided litigation support for various projects.
MORNING SEMINAR DETAILS
LOCATION
Simpson Gumpertz & Heger
135 South LaSalle Street, Suite 3800
Chicago, IL 60603
SCHEDULE
- 7:30 - 8:00 a.m. Registration & Coffee
- 8:00 - 9:30 a.m. Presentation & Discussion
- 9:30 - 10:00 a.m. Breakfast Reception
Click Here to Register for the Morning Session
EVENING SEMINAR DETAILS
LOCATION
The Conference Center at One North Wacker
1 N. Upper Wacker Drive, 2nd Floor
Chicago, IL 60606
SCHEDULE
- 4:00 - 4:30 p.m. Registration & Refreshments
- 4:30 - 6:00 p.m. Presentation & Discussion
- 6:00 - 6:30 p.m. Cocktail Reception
Click here to Register for the Evening Session